How PMOs improve Project Governance
Picture of Ken Burrell

Ken Burrell

One of the benefits of having a Project Management Office (PMO) is that good governance reduces the risks of project delivery and increases its predictability. 

Here’s an explanation of how this works in practice using as a case study a Portfolio PMO that I managed.

The organisation ran a fairly large number of relatively short term projects to set up software systems for new distribution clients. These Client Onboarding projects were run by project managers, but without reference to a documented methodology or a central co-ordinating body. The timescales were often unrealistically tight, and projects would often either miss the due date, or would overspend on additional resources in order to meet the due date.

The tight timescales were usually imposed as a result of sales representatives making ambitious promises to clients without reference to the organisation’s capacity to deliver. Overspend to achieve the deadlines was authorised by the same sales representatives that set the deadlines, but the money to fund the overspend did not come from the Sales budget, and no assessment was made of the effect of the increased effort on the other projects under way.

We were tasked with turning this situation around.

We made the following changes:

  • We set up a “pipeline” list of all the projects likely to be started in the near future, and put in place an approval mechanism so that no new projects (including client onboarding) would be started without the approval of a Portfolio Board.
  • We developed a monitoring approach to enable the Portfolio Management Office (PfMO) to detect situations where a project Change Request may be required. A discussion between the PM and the PfMO would be prompted by the triggering of either of two indicators:
    • Finances: Actuals to Date and Estimates At Completion (EAC) were monitored against approved Budgets At Completion (BAC), with indicators to show when EAC exceeded BAC by more than a tolerance amount (expressed in both absolute and relative terms).
    • Schedule: Key project milestones were monitored, with indicators to show if these were forecast to be late against the baselined dates.
  • We measured changes from baseline on both a cumulative and incremental basis, to prevent large changes being concealed as a series of small changes.
  • We escalated the authorisation of Project Change Requests to an organisational level dependent on the size of the change (in terms of costs, time, and business value)
  • We devised templates to support PMs in requesting changes and determining the approval level required, and monitored numbers of approved and rejected changes (to identify “noisy” projects).

As a result, project changes were reviewed and approved at an appropriate organisational level, the highest of which included a full review of the change impact on the rest of the portfolio. In the space of a year, this (along with other initiatives) moved the Client project portfolio from a situation in which all Client projects missed either time or budget constraints (and around 15% missed both!) to a situation in which just 20% of Client projects missed time or budget constraints, and none missed both.

Even if you are cynical and take the view that implementing such a Change Request process merely sanctions the breaking of initial Time and Cost constraints, then at the very least it ensures this is done with eyes open and in the full knowledge of the impact on the project portfolio as a whole.

This approach reduces the execution risk to the portfolio, and enables the Portfolio Board to consciously decide where to focus the organisation’s limited resources.

If you would like to have the benefits of an approach like this but would prefer not to get bogged down in the detail, The PMO Professionals can help. Why not take a look at our “Goal-oriented governance” service, and if that looks interesting, why not contact us to discuss how we can help you?
Featured articles
Visionary PMO Services Leadership Award 2025
Visionary PMO Services Leaders of the Year 2025
17 October 2025
Best-PMO
What Makes a Great PMO? Insights from Award-Worthy Examples
20 May 2025
Team picture
We only went and WON! A write-up of the Project Hack 23 winning entry
25 November 2024
The Art and Science of PMO – Part 3
4 September 2024
The Art and Science of PMO – Part 2
28 August 2024
The Art and Science of PMO – Part 1
21 August 2024
2024 PMO Research Report
Is the PMO its own worst enemy?
14 May 2024
Best PMO Tools
What are PMO Tools?
16 May 2023
The PMO Lifecycle
REVIEW: The PMO Lifecycle by William Dow, PMP
15 September 2022
What is a PMO?
30 June 2022
pmo-consultancy

6 Palmer Crescent

Leighton Buzzard

LU7 4HT

United Kingdom

Case Studies
Reducing project funding request rejection by improving quality of submissions
Promoting good project management practice
Keeping projects on time and on budget by keeping project changes in check
Increasing transparency of project cost performance vs. budget
Improving portfolio transparency with a financial framework
© 2026

The PMO Professionals Limited. All rights reserved.

Terms & conditions
Privacy policy
Linkedin Youtube
Go to Top
  • Home
  • Posts
  • Contact